Orchards as on 31-Aug-2019 |
|||
Description of Tower | Construction Stage | Next Month Planning | Remarks |
Orchards(A-1) | Casting of 20th FRS is completed. Also half slab upto 21st FRS is completed | Casting of full 21st FRS will continue | The 13th floor is numbered as 14th floor in these towers and thereafter 15th onwards |
Orchards(A-2) | Casting of full 14th FRS is completed. Also half slabs upto 15th floor roof are completed | Casting of full 15th FRS will be in progress | |
Orchards(A-3) | Casting of full 14th FRS is completed. Also half slabs upto 16th floor roof are completed | Casting of full 15th FRS will continue | |
Orchards(B-1) | Casting of 32nd FRS in progress | Casting of 32nd FRS will continue | |
Orchards(B-2) | Casting of 24th FRS in progress | Casting of 24th FRS will continue | |
Orchards(B-3) | Casting of 23rd FRS in progress | Casting of 23rd FRS will continue | |
Orchards(B-4) | Casting of 26th FRS in progress | Casting of 26th FRS will continue | |