Krescent Homes as on 31-May-2019 |
|||
Description of Tower | Construction Stage | Next Month Planning | |
Krescent Homes Tower-1 | Plaster and other civil works in progress | Plaster and other civil works will be in progress | |
Krescent Homes Tower-2 | Casting of full 18th FRS is completed. Also half slabs upto 22nd floor roof are completed | Casting of full 19th FRS will be in progress | |
Krescent Homes Tower-3 | Casting of full 12th FRS is completed. Also half slabs upto 13th floor roof are completed | Casting of full 13th FRS will be in progress | |
Krescent Homes Tower-4 | Casting of full 26th FRS is completed. Also half slabs upto 27th floor roof are completed | Casting of full 27th FRS will be in progress | |
Krescent Homes Tower-5 | Casting of full 9th FRS is completed. Also half slab completed upto 11th floor roof. | Casting of full 10th FRS will be in progress | |
Krescent Homes Tower-6 | Casting of 1st FRS in progress | Casting of 1st FRS will be in progress | |
Krescent Homes Tower-7 | Casting of half slab 1st FRS is completed | Casting of full 1st FRS will be in progress | |
Krescent Homes Tower-8 | Casting of full 19th FRS is completed. | Casting of 20th FRS will be in progress | |
Krescent Homes Tower-9 | Casting of full 25th FRS is completed. Also half slab of 26th FRS is completed | Casting of full 26th FRS will be in progress. | |
Krescent Homes Tower-10 | Plaster and other civil works in progress | Plaster and other civil works will continue | |
Krescent Homes Tower-11 | Casting of 28th FRS in progress | Casting of 28th FRS will be in progress | |
Krescent Homes Tower-12 | Casting of 28th FRS in progress | Casting of 28th FRS will continue | |
Krescent Homes Tower-14 | Casting of full 28th FRS is completed | Plaster and other civil works will be in progress | |
Krescent Homes Tower-15 | Casting of full 25th FRS is completed. | Casting of 26th FRS will be in progress. | |
Krescent Homes Tower-16 | Plaster and other civil works in progress | Plaster and other civil works will continue | |
Krescent Homes Tower-17 | Casting of full 27th FRS is completed | Casting of 28th FRS will be in progress | |
Krescent Homes Tower-18 | Casting upto full 9th FRS is completed. Also half slabs upto 12th floor roof are completed | Casting of full 10th FRS will be in progress. | |
Krescent Homes Tower-19 | Casting of full 20th FRS is completed. Also half slabs upto 24th floor roof are completed | Casting of full 21st FRS will be in progress | |
Krescent Homes Tower-20 | Casting of GFRS is in progress | Casting of GFRS will continue | |
Krescent Homes Tower-21 | Casting of full 27th FRS is completed. | Casting of 28th FRS will be in progress | |
Krescent Homes Tower-22 | Plaster and other civil works in progress | Plaster and other civil works will be in progress | |
Krescent Homes Tower-23 | Casting of full 8th FRS is completed. Also half slab upto 9th FRS is completed. | Casting of full 9th FRS will be in progress. | |
Krescent Homes Tower-24 | Casting of GFRS in progress | Casting of GFRS will continue |