Kosmos
Description of Tower Construction Stage Next Month Planning Remarks
Kosmos-1 Offers of possession sent    
Kosmos-2 Offers of possession sent    
Kosmos-3 Offers of possession sent    
Kosmos-4 Offers of possession sent    
Kosmos-5 Offers of possession sent    
Kosmos-6 Offers of possession sent    
Kosmos-7 Offers of possession sent    
Kosmos-8 Offers of possession sent    
Kosmos-9 Offers of possession sent    
Kosmos-10 Offers of possession sent    
Kosmos-11 Offers of possession sent    
Kosmos-12 Offers of possession sent    
Kosmos-14 Offers of possession sent    
Kosmos-15 Offers of possession sent    
Kosmos-16 Offers of possession sent    
Kosmos-17 Offers of possession sent    
Kosmos-18 Offers of possession sent    
Kosmos-19 Offers of possession sent    
Kosmos-20 Offers of possession sent    
Kosmos-21 Offers of possession sent    
Kosmos-22 Offers of possession sent    
Kosmos-23 Brickwork and plaster works in progress Brickwork and plaster works will continue  
Kosmos-24 Brickwork and plaster works in progress Brickwork and plaster works will continue  
Kosmos-25 Brickwork and plaster works in progress Brickwork and plaster works will continue  
Kosmos-26 Internal plaster, flooring and other finishing works in progress Internal plaster, flooring and other finishing works will be in progress.  
Kosmos-28 Offers of possession sent    
Kosmos-29 Offers of possession sent    
Kosmos-30 Offers of possession sent    
Kosmos-31 Offers of possession sent    
Kosmos-32 Offers of possession sent    
Kosmos-33 Offers of possession sent    
Kosmos-34 Offers of possession sent    
Kosmos-35 Offers of possession sent    
Kosmos-36 Offers of possession sent    
Kosmos-37 Offers of possession sent    
Kosmos-42 Offers of possession sent    
Kosmos-43 Offers of possession sent    
Kosmos-44 Internal plaster and flooring is in progress Internal plaster and flooring will continue  
Kosmos-45 Internal plaster and flooring is in progress Internal plaster and flooring will continue  
Kosmos-46 Internal plaster and flooring is in progress Internal plaster and flooring will continue  
Kosmos-47 Internal plaster and flooring is in progress Internal plaster and flooring will continue  
Kosmos - 51 Offers of possession sent    
Kosmos - 52 Offers of possession sent    
Kosmos - 53 Offers of possession sent    
Kosmos - 54 Internal plaster and flooring is in progress Internal plaster and flooring will continue  
Kosmos - 55     Construction Of Towers Is On Hold
Kosmos- 56    
Kosmos - 57    
Kosmos - 57A    
Kosmos - 59    
Kosmos - 60 Internal plaster and flooring is in progress Internal plaster and flooring will continue  
Kosmos - 61 Internal plaster and flooring is in progress Internal plaster and flooring will continue  
Kosmos - 62 Offers of possession sent    
Kosmos - 63 Offers of possession sent    
Kosmos - 64 Offers of possession sent    
Kosmos - 65 Offers of possession sent    
Kosmos - 66 Internal plaster and flooring is in progress Internal plaster and flooring will continue  
Kosmos - 67 Internal plaster and flooring is in progress Internal plaster and flooring will continue  
Kosmos - 68 Internal plaster and flooring is in progress Internal plaster and flooring will continue  
Kosmos - 69 Internal plaster and flooring is in progress Internal plaster and flooring will continue  
Kosmos - 70 Internal plaster and flooring is in progress Internal plaster and flooring will continue  
Kosmos - 71 Internal plaster and flooring is in progress Internal plaster and flooring will continue  
Kosmos - 72 Internal plaster and flooring is in progress Internal plaster and flooring will continue  
Kosmos - 72 A Internal plaster and flooring is in progress Internal plaster and flooring will continue  
Kosmos - 72B Internal plaster and flooring is in progress Internal plaster and flooring will continue  
Kosmos - 72C Casting of 19th FRS in progress Casting of 19th FRS will continue  
Kosmos - 79A Brickwork and plaster works in progress Brickwork and plaster works will be in progress  
Kosmos - 79B Casting of 16th FRS in progress Casting of 16th FRS will continue  
Kosmos - 58 Internal plaster and flooring is in progress Internal plaster and flooring will continue  
Kosmos- 73 Offers of possession sent    
Kosmos - 74 Internal plaster and flooring is in progress Internal plaster and flooring will continue  
Kosmos- 75 Internal plaster and flooring is in progress Internal plaster and flooring will continue  
Kosmos - 77 Internal plaster and flooring is in progress Internal plaster and flooring will continue  
Kosmos - 78 Internal plaster and flooring is in progress Internal plaster and flooring will continue  
Kosmos - 79 Brickwork and plaster works in progress Brickwork and plaster works will continue  
Kosmos - 80 Brickwork and plaster works in progress Brickwork and plaster works will continue