Kasa Isles as on 31-May-2019 |
|||
Description of Tower | Construction Stage | Next Month Planning | |
Kasa Isle (Tower-1) | Internal plaster and flooring is in progress | Internal plaster and flooring will continue | |
Kasa Isle (Tower-2) | Internal plaster and flooring is in progress | Internal plaster and flooring will continue | |
Kasa Isle (Tower-3) | Brickwork and plaster in progress | Brickwork and plaster will be in progress | |
Kasa Isle (Tower-4) | Brickwork and plaster in progress | Brickwork and plaster will be in progress | |
Kasa Isle (Tower-5) | Casting of 25th FRS in progress | Casting of 25th FRS will continue | |
Kasa Isle (Tower-6) | Brickwork and plaster in progress | Brickwork and plaster will be in progress | |
Kasa Isle (Tower-7) | Brickwork and plaster in progress | Brickwork and plaster will be in progress | |
Kasa Isle (Tower-8) | Brickwork and plaster in progress | Brickwork and plaster will be in progress | |
Kasa Isle (Tower-9) | Brickwork and plaster in progress | Brickwork and plaster will be in progress | |
Kasa Isle (Tower-10) | Brickwork and plaster in progress | Brickwork and plaster will be in progress | |
Kasa Isle (Tower-11) | Brickwork and plaster in progress | Brickwork and plaster will be in progress | |
Kasa Isle (Tower-12) | Internal plaster and flooring is in progress | Internal plaster and flooring will continue | |
Kasa Isle (Tower-14) | Internal plaster and flooring is in progress | Internal plaster and flooring will continue | |
Kasa Isle (Tower-15) | Brickwork and plaster in progress | Brickwork and plaster will be in progress | |
Kasa Isle (Tower-16) | Brickwork and plaster in progress | Brickwork and plaster will be in progress |